Activity
Determine the maximum amount of time that can be planned for this activity per day. This causes vPlan to schedule excess hours to the next day(s).
Determine if the acitivity is billable.
Set the hourly rate of the activity.
Activity
id
string <uuid>
read-onlyoptional
description
string
optional
code
string
optional
item_id
string <uuid>
optional
resource_type
enum<string>
optional
Allowed values:
resourcemachinecell
Default:
resource
default_duration
integer
optional
day_max_duration
integer
optional
billable
boolean
optional
hourly_rate
integer
optional
position
integer
optional
time
integer
optional
time_remaining
integer
optional
time_original
integer
optional
external_ref
string | null
read-onlyoptional
Example:
fb1033a2ed70
created_at
string <date-time>
read-onlyoptional
Example:
2024-04-11T10:22:15Z
updated_at
string <date-time>
read-onlyoptional
Example:
2024-04-11T10:22:15Z
archived_at
string <date-time>
read-onlyoptional
Example:
2021-07-06T11:24:35Z